March 2022

28/03/2022 by Steiner SA

In March, Steiner teams continued the construction of the structure of the extension to the Ecolint International School of Geneva. This structural phase will be completed in April 2022 before the waterproofing work begins. See the latest progress in our video.

Continue Reading

February 2022

14/02/2022 by Steiner SA

The Ecolint-EYE project is taking shape on the Ecolint Nations campus. In February, Steiner’s teams continued with the structural work. The structures are coming out of the ground and the first floors are already built. Discover the progress of the project in our latest video.

Continue Reading

Video of the Ecolint extension with computer generated images

09/12/2021 by Steiner SA

To close the year 2021, Steiner is offering you a look at its extension project of the International School of Geneva (Ecolint). The year 2021 saw the project start with the demolition of the old site facilities. Steiner then continued the project by carrying out the earthworks and the installation of the Canadian well before …

Continue Reading

November 2021

02/12/2021 by Steiner SA

The structural work continued in November on the Ecolint extension site in Geneva. Steiner’s teams supervised the construction of the invert and the first load-bearing elevations of the new building. The superstructure of the building will rise over the next few months. The video shows the start of the underground waterproofing as well as all …

Continue Reading

September 2021

12/10/2021 by Steiner SA

The Ecolint extension project progressed in September 2021. The Steiner SA teams have completed part of the foundations for the new building and erected the crane. The structural work will now be carried out on site. The structures of the building will emerge in the coming months. The first educational visits took place while the …

Continue Reading

August 2021

06/10/2021 by Steiner SA

In August, the headquarters was installed on the Ecolint construction site. This will house the construction management and provide changing rooms and a refectory for the subcontractors. The video also shows the start of the installation of the Canadian well. Thanks to pipes buried in the ground, this air circuit makes it possible to use …

Continue Reading

July 2021

10/08/2021 by Steiner SA

At the beginning of July, the demolition of the old facilities is coming to an end. The concrete from the old structures is being crushed on site. The earthworks have also begun.

Continue Reading

June 2021

16/08/2021 by Steiner SA

Steiner installs the fences and the site sign. The earthworks on the site have started. New connections for water and electricity are established.

Continue Reading

May 2021

10/08/2021 by Steiner SA

The building permit goes into effect. Steiner begins demolition of the sports facilities on the site of the new extension.

Continue Reading