Ecolint-EYE: March 2023

03/03/2023 by Steiner SA

The exterior work is nearing completion, with the planting and children’s playground equipment now in place. The interior finishing touches to the building are nearing completion with the installation of the atrium screens. On the technical side, commissioning has started and the first equipment in the building is in operation, such as the lighting in …

December 2022 and January 2023

09/02/2023 by Steiner SA

The external works are progressing well, the canopy at the main entrance is being completed while the interior finishing touches are being put in place with the laying of the vinyl floors in the classrooms and the Haltopex floors in the atrium ramp. On the technical side, all the lighting fixtures have been installed and …

October et November 2022

16/12/2022 by Steiner SA

During these two months, the brick facades are being finished and the insulation for plastering some of the walls is being installed. The external fittings on the roof and on the periphery of the building are continuing, and the large structural elements have been completed, the crane has been dismantled. Inside the building, the installation …

September 2022

18/10/2022 by Steiner SA

In September, the Steiner teams can remove the scaffolding as the railings are installed and the waterproofing resin is applied to the passageways. The exterior brick facades continue to be laid from the bottom to the top, at the same time as the exterior fittings progress gradually with the pouring of sandblasted concrete and the …

August 2022

01/09/2022 by Steiner SA

In August, work began on the brick facades with completion scheduled for the end of October 2022. Meanwhile, the external works continue and the existing schoolyard was refurbished over the summer and for the start of the new school year with the laying of new paving stones to link with the new building. Inside, the …

July 2022

01/09/2022 by Steiner SA

In July, the Steiner teams completed the waterproofing work. The closed part of the building is also nearing completion, with the installation of the last of the exterior joinery and the glass for the roof window. The exterior brick facades are beginning with the insulation, at the same time as the exterior fittings with the …

June 2022

06/07/2022 by Steiner SA

In June, the Steiner teams continued the waterproofing work. The structure of the glass roof was installed and then provisionally waterproofed while waiting for the glass to be installed at the beginning of July. Meanwhile, the technical work inside the building (electricity, heating, sanitary facilities, etc.) and the plasterboard partitions are being installed to allow …

May 2022

01/06/2022 by Steiner SA

In April and May, Steiner teams continued the construction of the structure of the extension to the Ecolint International School of Geneva. With the structural phase almost complete, the insulation work will begin at the end of May 2022. Meanwhile, the technical work inside the building (electricity, heating, sanitary facilities, etc.) will follow. Discover the …

March 2022

28/03/2022 by Steiner SA

In March, Steiner teams continued the construction of the structure of the extension to the Ecolint International School of Geneva. This structural phase will be completed in April 2022 before the waterproofing work begins. See the latest progress in our video.

February 2022

14/02/2022 by Steiner SA

The Ecolint-EYE project is taking shape on the Ecolint Nations campus. In February, Steiner’s teams continued with the structural work. The structures are coming out of the ground and the first floors are already built. Discover the progress of the project in our latest video.