In July, the Steiner teams completed the waterproofing work. The closed part of the building is also nearing completion, with the installation of the last of the exterior joinery and the glass for the roof window.
The exterior brick facades are beginning with the insulation, at the same time as the exterior fittings with the construction of the retaining walls and concrete stairs as well as the earthworks.
Finally, inside, the plasterboard partitions have been completed, and the floor insulation and underfloor heating are being installed so that the screed can be poured.

Share on Social Media
twitter facebook linkedin emailwhatsapp

Post navigation

Previous Post:

June 2022

Next Post:

August 2022

Réseaux sociaux

  • Youtube
  • Instagram
  • LinkedIn
© 2023 Chantier Ecolint-EYE | WordPress Theme by Superbthemes